Rise and Build-February Update

RISE AND BUILD
February 2023 Update


February has arrived, the month where love is in the air as we approach Valentine’s Day. With our attention placed on thoughts of love, our love for future generations is demonstrated in our continued progress with the Rise and Build campaign. Here are the latest accomplishments with this project…

· A custom window has been cut, built, painted, and installed in the Pizza room.
· A countertop has been stained, sealed, and installed in the Pizza room.
· Trim on the exterior of the Pizza room has been installed.
· Eight booths have been rebuilt in the Pizza room.
· A chalkboard and a TV have been installed in the Pizza room.
· In the Candy room, a TV has been installed.
· Walls have been prepped in the Theater.
· In the Women’s restroom, a countertop, sinks, and automatic faucets have been installed. Additionally, the sinks have been caulked.
· LVT tile has been laid in the Men’s restroom.
· Installation of new ceiling tiles in both restrooms has been completed.
· Painting has been completed in the following areas: cabinets, a white board, a butcher block, three doors, the ticket booth, a window, the trim in the Pizza room, as well as clouds on two walls.
· Booths and café tables have been refurbished in new areas.
· New tables and chairs have arrived for the kids’ game room.
· Wires have been run from the main board in the green room to blowers in the bathrooms on the mezzanine level.
· Carpet is being installed in the mezzanine level.

A great deal of progress has been made, demonstrating the great deal of love we have for the upcoming generations. Thank you for the love you have shown through your continued prayer and support as we continue to Rise and Build!