Rise and Build-March Update

Time has changed. Days are getting longer, and nights are getting shorter. As the season has changed, our level of progress on the Rise and Build campaign has changed as well. Here are some of the recent changes in our ongoing progress…
· The following tasks were completed in the children’s area atrium: repaired and painted east and south walls, two double doors, and single door and trim; removed, painted and reinstalled six wall sconces; rebuilt and rewired internal components on six wall sconces; removed light under stairs; removed surface mounted wiring and installed new wiring for TV under stairs; removed seven old chandeliers; installed two new fans; installed six new high bay lights; added one new lighting circuit on the north end; removed the check-in kiosk from the wall and installed legs on the kiosk to make it free standing.
· In the atrium’s adjoining hall, the following tasks were completed: removed old ceiling tile and installed new ceiling tile; removed old base; removed old speakers; repaired and painted all walls and ceilings; painted trim on double case opening, fire extinguisher case, two doors and trim, and four can lights; replaced old exit sign; installed five new diffusers on lights; repaired ceiling grid; relocated WiFi booster.
Although times and seasons may change, nothing will change about our commitment to providing excellent facilities for the next generation. Thank you for your ongoing prayer and support as we continue to Rise and Build!
· The following tasks were completed in the children’s area atrium: repaired and painted east and south walls, two double doors, and single door and trim; removed, painted and reinstalled six wall sconces; rebuilt and rewired internal components on six wall sconces; removed light under stairs; removed surface mounted wiring and installed new wiring for TV under stairs; removed seven old chandeliers; installed two new fans; installed six new high bay lights; added one new lighting circuit on the north end; removed the check-in kiosk from the wall and installed legs on the kiosk to make it free standing.
· In the atrium’s adjoining hall, the following tasks were completed: removed old ceiling tile and installed new ceiling tile; removed old base; removed old speakers; repaired and painted all walls and ceilings; painted trim on double case opening, fire extinguisher case, two doors and trim, and four can lights; replaced old exit sign; installed five new diffusers on lights; repaired ceiling grid; relocated WiFi booster.
Although times and seasons may change, nothing will change about our commitment to providing excellent facilities for the next generation. Thank you for your ongoing prayer and support as we continue to Rise and Build!